Project
Barricade, Tema Industrial Area
Description
Duration: 7 days
Client : Ghana Petroleum Mooring System
Agreed scope of works:
1.Installation of Reinforced Jersey Barriers along pipeline servitude
2.Painting of all jersey barriers and stencil caution notes/signs on them
Project Location: Tema Industrial Area-Ghana
The entire project was to deter illegal activities carried being carried out on an operational pipeline route. Activities included dumping of metal scrap, camping grounds for squatters, burning of rubbish and the use of some areas as parking spots and access routes for Bulk Road Vehicles.
At Tramos safety being a key element we had a safety officer to ensure we comply with all applicable safety standards to protect workers and properties by clearly marking out with warning signs and yellow plastic tape fixed to wood posts.By these protocols the project was executed safely and accident free.